OPEN!

The bathrooms on 6 are open! 

Lights and fans come on and turn off automatically when someone enters and leaves! So, please do not use the wall switches. Thanks and enjoy. 




Tuesday, November 24, 2015

Almost Complete

The building is almost complete! Plumbers are here this morning, and if all goes right the Bathrooms will be open for use by Friday if not Sooner! 
I'll post interior pictures once toilets and sinks are installed. 





Friday, November 13, 2015

Thursday, November 12, 2015

Wednesday, November 4, 2015

#6 building update!


Going good ! 

Foundation built, plumbing laid, floor poured and stamped. Floor scheduled to be sealed today and building framed tomorrow, weather depending.